July 31, 2024 Update
Construction on Doncaster Drive will begin the week of August 19, 2024. Beverly Road and the majority of Danbury Street will be constructed in the spring, with a final completion date of May 31, 2025. Thank you for everyone’s patience as we confirmed these dates with the contractor, S&L Underground. View updated plans.
View the linked fact sheet for more information.View past project updates »
Project Details
- Location
- 4240 Beverly Road
Madison, WI 53711
- 4240 Beverly Road
- Project TypeRoad Construction
- StatusIn Design
- Estimated ScheduleAugust 5, 2024 – May 30, 2025
- ImpactMajor
- Alder DistrictDistrict 10
- Contract Number8709
Map Data
Project Information
Project Overview
The overall project includes full pavement reconstruction, new curb & gutter, new sidewalk, replacement of sanitary and water mains, and replacement of storm sewer where necessary.
Doncaster Drive, Beverly Road, and Danbury Street are being reconstructed with new curb & gutter and sidewalk. Parking will be allowed on one side only. The terrace (between the sidewalk and street) will be 2.5 ft. The options in Exhibit A have been developed to reflect three competing priorities: pedestrian safety and convenience, maintenance of existing trees, and proper street width.
Project Limits
Doncaster Drive – Danbury Street to Seminole Highway
Beverly Road – Wenona Way to Seminole Highway
Danbury Street – Doncaster Road to Mohawk Drive
Project Schedule
Design: 2024
Construction: 2024
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:
Public Information Meetings
March 21, 2024 Public Information Meeting Recording
March 21, 2024 Public Information Meeting PowerPoint Presentation
If you need an interpreter, translator, materials in alternate formats or other accommodations to access this service, activity or program, please call Mario Galindez of the Engineering Division at 608-266-4095.
Si necesita un intérprete, un traductor, materiales en formatos alternativos u otros arreglospara acceder a este servicio, actividad o programa, llama Mario Galindez en el departamento de ingenieria municipal inmediatamente a (608) 266-4095.
Yog tias koj xav tau ib tug neeg txhais lus, ib tug neeg txhais ntawv, cov ntaub ntawv ua lwm yam los sis lwm cov kev pab kom siv tau qhov kev pab, kev ua num los sis kev pab cuam no, thov hu rau tus xov tooj hauv qab no tam sim no.
City Process, Meetings
The design team will present the street layout options to the Transportation Commission March 27, 2024
Board of Public Works: April 17, 2024
Common Council: May 7, 2024
Mailings
Board of Public Works: April 17, 2024 Notice of Meeting Fact and Details Sheet Schedule of Assessments