Location
53711 Madison , WI
43° 2′ 51.5364″ N, 89° 26′ 57.066″ W
Last Updated: 11/08/2019
Last Updated: 10/10/2019
Pre-Construction Meeting
The pre-construction meeting will occur October 14, 2019 at City Engineering offices. Construction is expected to start October 28, 2019.
Project Bidding Complete
The project was advertised for Bid on August 22nd, 2019. The second advertisement occurred on August 29th, 2019. The Bid Opening will occurred on September 5th, 2019. A recommendation has been made to award the contract. Bid information can be found: Public Works Contracts Webpage
Public Information Meeting
Time: July 11th, 6:00 pm
Location: Thoreau Elementary School Library, 3870 Nakoma Road
Project Description
In 2017, the original stone arch culvert under the Southwest Bike Path at Waite Circle began to fail. In 2017, as a result of the impending failure, the arch was slip lined with a 60-inch culvert during an emergency repair.
This project will reconstruct the culvert to a size similar to that of the existing arch, with provisions to modify the opening size once the Wingra West Watershed Study is complete. The culvert reconstruction will occur in late 2019. In addition to the culvert reconstruction, the Madison Metropolitan Sewerage District Intercept beneath the culvert will be reconstruction and relocated adjacent to the proposed box culvert. Other minor repairs will be made to infrastructure in the immedate project area.
The City hosted a public information meeting to discuss the components of the project, including the bike path detour that will occur during construction. The presentation can be found: July 11 2019 Public Information Meeting Presentation PDF .